Abandoned Mine Lands Program
INTRODUCTION
The federal Surface Mining Control and Reclamation Act was
signed into law on August 3,1977 to regulate surface coal mining and reclamation nationwide. The law provided states the opportunity to develop State coal programs and assume primacy over the coal program from
the federal government. Alaska chose to administer the program and the Alaska
Surface Coal Mining Control and Reclamation Act was approved on May 2,1983 with
the Commissioner of the Department of Natural Resources being granted
jurisdiction over surface coal mining and reclamation operations in the state.
In addition to regulating the coal industry the State and federal laws created
the Abandoned Mine Lands Program for the purpose of reclaiming abandoned
historic mines of any type.
Land and water eligible for reclamation are those that
were mined or affected by mining and abandoned or left in an inadequate
reclamation status before August 3, 1977, and for which there is no continuing
reclamation responsibility under State or federal law. AML funds can be spent
on coal and non-coal abandoned historic mines. State, private, native and
federal lands are eligible. Original sunset for the collection of AML funds was
in 2004, set by federal law. The fee
collection that provides the funds which the federal government distributes to
the various states and tribal entities has been extended essentially on a
year-by-year basis since that date. Several congressional efforts to date have failed to provide a long-term
solution to the funding issue. While
some State view the AML Program as an ongoing source of revenue, Alaska manages
the funding with an eye towards getting as many safety issues mitigated as
possible in the shortest time practicable given the funding level
provided. There are no State General
Fund dollars used in the AML Program.
Return to top
FUNDING SOURCE AND LEVELS
The AML Program is funded 100 percent by the AML Trust Fund
administered by the federal Office of Surface Mining Reclamation and
Enforcement (OSMRE). AML funds are collected from a fee assessed on today’s
coal industry for every ton of coal produced and used to correct past
deficiencies on now-defunct mine sites. The fee is 35 cents/ton for surface
mines and
15 cents/ton for underground mines.
The State is entitled to receive 50% of the fees
collected from coal production in the State, the historic production amount and
emergency funds. Alaska's funding level has historically been
less than $200,000 using this award formula. If a State's reclamation needs
exceed $2,000,000 they can request Minimum Program Status and receive
$1,500,000 plus emergency funds annually until the work remaining on the
inventory drops below the $2,000,000 level. Alaska has received the Minimum Program
funding level of grant amounts since 1994 (Figure 1).
Alaska has received $23.5 million since FFY 1983 (Figure 2). Funding should remain stable at $1,500,000 annually based upon the current AML inventory of coal and non-coal projects. The Minimum Program
Coalition has requested OSMRE to raise the funding level for minimum program
states to $2,000,000 as provided for in the federal law. Alaska could use the higher level of
funding. Some congressional initiatives would have the grants for minimum programs such as Alaska’s increase to $3.0 million per year and completely stop after an additional 15 years of activity.

The
majority of the AML funds ($1,195,000) are awarded to Alaskan contractors
(Figure 3). The cost of administering the program is only $305,000 a year. The
construction funds in each grant are available for three years. The
administrative and emergency funds are single year funds. Any balances at the
end of a grant cycle are rolled over to another grant.
Return to top
INVENTORY AND ACCOMPLISHMENTS Coal and non-coal abandoned historic mines were broadly inventoried.
Coal mining in Alaska
has been well documented and every mine of significance has been identified.
The coal inventory was completed in 1983 and 340 sites were identified. At present we are working to refine that
inventory to identify specific features and plan for mitigating each of them. A literature search of known non-coal mines
was compiled in 1991 and 432 sites were identified. The non-coal inventory remains
incomplete for state, private and native lands.
Every inventoried site was evaluated to determine if it
qualified for AML funding. Federal policy requires that priority one and two
coal projects (the most likely to cause death or severe injury to site
visitors) be completed first. Priority three coal projects (environmental
issues) can be completed in conjunction with priority one and two projects or
after all priority one and two projects have been completed. Only priority one
non-coal projects can be reclaimed. Priority one non-coal sites can be worked
on simultaneously with coal sites if they have been requested by the Governor.
Because of the subjective nature of the criteria priority two non-coal sites
were identified for further evaluation. The three reclamation priorities are:
1. Protection of public health, safety, general welfare and
property from extreme danger resulting from the adverse effects of past coal
mining practices.
2. Protection of public health, safety and general welfare
from adverse effects of past coal mining practices, which do not constitute an
extreme danger.
3. Restoration of eligible lands and waters and the
environment previously degraded by adverse effects of past coal mining
practices, including measures for the conservation and development for soil,
water (excluding channelization), woodland, fish and
wildlife, recreation resources, and agricultural productivity.
|
(Figure 4) AML Inventory as of Oct. 23, 2006 |
|
|
Coal Projects |
Non-Coal Projects |
|
Region |
Priority 1 |
Priority 2 |
Priority 3 |
Priority 1 |
Priority 2 |
Priority 3 |
|
Artic |
0 |
0 |
0 |
0 |
0 |
0 |
|
Interior |
6 |
7 |
1 |
4 |
0 |
0 |
|
Northwest |
0 |
0 |
0 |
0 |
0 |
0 |
|
Sount Central |
9 |
35 |
5 |
0 |
0 |
1 |
|
South East |
0 |
0 |
7 |
48 |
0 |
3 |
|
South West |
0 |
0 |
0 |
0 |
0 |
4 |
|
Subtotal |
15 |
42 |
13 |
52 |
0 |
8 |
|
Total by
Source |
|
70 |
|
|
60 |
|
Utilizing these general priorities it was determined that
there were some 70 coal projects areas and up to 60 known non-coal projects
that still need to be reclaimed (Figure 4).
In the initial inventories it was estimated that reclamation
of the coal projects would cost $52,000,000 and the non-coal projects would
cost $2,700,000. To date 45 AML projects have been completed at a cost of $13.7
million (Figure 5). In some cases a site contains a single mining hazard and in
other cases a multitude of mining hazards exists on a single site. The majority
of the remaining coal related hazards are dangerous highwalls
(12,500 feet) and the majority of the non-coal hazards are open portals and
vertical openings (49).
The goals of the AML Program will be to complete as many coal
and non-coal projects as funding will allow. We will be using periods of time
when most funds are committed to single large projects to define and design
mitigation plans for the remaining features requiring work in order to have the
projects “on the shelf” as funds become available in the future. Funding for non-coal projects is limited to
the state share ($140,070) and historic coal share ($20,407).
It is apparent that all of the sites requiring
reclamation cannot be completed before the AML Funds cease to be available in
the future. The Division will continue to re-evaluate the inventories and
concentrate on the highest priority coal and non-coal projects that have been
identified. The AML Program will attempt to find other sources of finding such
as shared cost projects with the mining industry, utilizing the RAMS Program
through the US Army Corps of Engineers, and leveraging project participation by
the various federal land managing agencies.
Return to top
|
(Figure 5) AML Accomplishments |
|
Problem Area |
Units * |
Problem Description |
Costs |
|
Bonanza Mine |
4 |
Portal(s) |
$9,924.00 |
|
Buffalo Mine |
1 |
Hazardous Equipment &
Facilities |
$15,000.00 |
|
|
1 |
Portal(s) |
$18,012.00 |
|
|
1 |
Vertical Opening |
$16,000.00 |
|
|
1.5 |
Gob Pile(s) |
$7,500.00 |
|
Carbon Run South |
4 |
Hazardous Equipment &
Facilities |
$27,500.00 |
|
Chickaloon Mine |
7 |
Hazardous Equipment &
Facilities |
$4,100.00 |
|
Chignik |
2 |
Portal(s) |
$36,210.00 |
|
Crowne Pointe Mine |
4 |
Portal(s) |
$11,000.00 |
|
|
1 |
Vertical Opening |
$10,500.00 |
|
Culross Mine |
1 |
Vertical Opening |
$61,598.00 |
|
|
1 |
Portal(s) |
$52,280.00 |
|
Diamond Mine |
2 |
Dangerous Impoundments |
$13,600.00 |
|
|
2 |
Hazardous Equipment &
Facilities |
$3,238.00 |
|
|
30 |
Dangerous Highwalls |
$6,000.00 |
|
Dunkle Mine |
14 |
Hazardous Equipment &
Facilities |
$33,775.00 |
|
East Houston Mine |
2 |
Vertical Opening |
$10,000.00 |
|
|
4 |
Hazardous Equipment &
Facilities |
$20,000.00 |
|
|
900 |
Dangerous Highwalls |
$33,200.00 |
|
Erie Mine |
2 |
Portal(s) |
$29,729.00 |
|
Eska Mine |
1 |
Portal(s) |
$25,000.00 |
|
|
2 |
Hazardous Equipment &
Facilities |
$21,000.00 |
|
|
5 |
Gob Pile(s) |
$3,993.00 |
|
|
9 |
Slurry |
$10,000.00 |
|
Glenn Highway Adits |
2 |
Portal(s) |
$10,973.00 |
|
Gold Standard Mine |
10 |
Portal(s) |
$87,000.00 |
|
|
2 |
Vertical Opening |
$9,700.00 |
|
Grenac Claims |
4 |
Vertical Opening |
$7,370.00 |
|
Hammond River |
2 |
Hazardous Equipment &
Facilities |
$51,060.00 |
|
Happy Association Claims |
2 |
Vertical Opening |
$3,600.00 |
|
Healy Creek Floodplain |
1350 |
Hazardous Equipment &
Facilities |
$868,535.00 |
|
Jonesville Fire |
35.8** |
Surface Burning |
$4,396,438.00 |
|
Jumbo Mine |
4 |
Portal(s) |
$9,924.00 |
|
Kuk River |
1 |
Hazardous Equipment &
Facilities |
$976.00 |
|
|
1 |
Portal(s) |
$1,500.00 |
|
|
2 |
Industrial/Residential Waste |
$3,200.00 |
|
Little Eva Mine |
1 |
Portal(s) |
$200.00 |
|
|
3 |
Vertical Opening |
$3,396.00 |
|
Londevan Mine |
1 |
Portal(s) |
$29,500.00 |
|
McKinley Lake Mine |
1 |
Hazardous Equipment &
Facilities |
$7,500.00 |
|
|
1 |
Portal(s) |
$15,000.00 |
|
|
3 |
Vertical Opening |
$15,000.00 |
|
Mead River Mine |
1 |
Hazardous Equipment &
Facilities |
$200.00 |
|
|
1 |
Vertical Opening |
$277.00 |
|
Nenana River Tramway |
5 |
Hazardous Equipment &
Facilities |
$7,000.00 |
|
North Fork Chandalar River |
5 |
Hazardous Equipment &
Facilities |
$8,053.00 |
|
North Jones Mine |
1 |
Dangerous Impoundments |
$50,000.00 |
|
|
5300 |
Dangerous Highwalls |
$2,903,782.00 |
|
Paige Shaft |
1 |
Vertical Opening |
$7,932.00 |
|
Peterson Mine |
1 |
Vertical Opening |
$9,093.00 |
|
Red Top Mine - Denali |
1 |
Portal(s) |
$22,812.00 |
|
|
2 |
Dangerous Piles & Embankments |
$5,000.00 |
|
Sagan Bench Claims |
4 |
Vertical Opening |
$7,200.00 |
|
Shoup Bay/Alice Mine |
1 |
Portal(s) |
$10,150.00 |
|
|
1 |
Vertical Opening |
$54,880.00 |
|
Six Mile Mine |
2 |
Portal(s) |
$8,341.00 |
|
South Knob Creek Mine |
1 |
Dangerous Impoundments |
$15,762.00 |
|
|
1 |
Dangerous Piles & Embankments |
$925.00 |
|
|
25 |
Slump |
$11,000.00 |
|
|
30 |
Dangerous Highwalls |
$3,000.00 |
|
Southeast Knob Creek |
2 |
Hazardous Water Body |
$123,640.00 |
|
|
47 |
Spoil Area |
$84,935.00 |
|
|
4860 |
Dangerous Highwalls |
$3,305,443.00 |
|
Suntana Townsite |
1 |
Hazardous Equipment &
Facilities |
$18,300.00 |
|
Suntrana Old Tipple |
1 |
Hazardous Equipment &
Facilities |
$20,000.00 |
|
|
1 |
Industrial/Residential Waste |
$530,000.00 |
|
Suntrana Tipple |
60** |
Hazardous Equipment &
Facilities |
$25,344.00 |
|
Suntrana Townsite |
1 |
Industrial/Residential Waste |
$3,800.00 |
|
|
11 |
Hazardous Equipment &
Facilities |
$18,300.00 |
|
Sutton Coal Washery |
1 |
Hazardous Equipment &
Facilities |
$20,284.00 |
|
Treadwell Mine |
5 |
Hazardous Equipment &
Facilities |
$73,000.00 |
|
|
5 |
Portal(s) |
$90,804.00 |
|
|
12 |
Vertical Opening |
$210,077.00 |
|
|
70 |
Dangerous Highwalls |
$13,350.00 |
|
Vitro Railroad Tipple |
3.5 |
Dangerous Piles & Embankments |
$12,034.00 |
|
|
5 |
Hazardous Equipment &
Facilities |
$10,666.00 |
|
West Homer Mine |
2 |
Vertical Opening |
$51,474.00 |
|
Wishbone Hill Mine |
1 |
Portal(s) |
$1,500.00 |
|
|
3 |
Hazardous Equipment &
Facilities |
$9,225.00 |
|
Grand Total |
|
|
$13,747,614.00 |
|
** Project is partially completed. |
|
|
|
|
|
|
|
|
|
*
Problem Area Work Unit Measurements |
|
Problem Description |
Standard Measurement Unit |
Completed as of 10/23/2006 |
|
Dangerous Highwalls |
Feet |
11,190 |
|
Dangerous Impoundments |
Count |
4 |
|
Dangerous Pile & Embankments |
Acres |
6.5 |
|
Gob Piles |
Acres |
6.5 |
|
Hazardous Equipment &
Facilities |
Count |
1,486 |
|
Hazardous Water Body |
Count |
2 |
|
Industrial/Residential Waste |
Acres |
4 |
|
Portals |
Count |
45 |
|
Spoil Area |
Acres |
47 |
|
Surface Burning |
Acres |
35.8 |
|
Slurry |
Acres |
9 |
|
Slumps |
Acres |
25 |
|
Vertical openings |
Count |
41 |
|
|
|
|
|
Return to top
For more information
contact:
Division of Mining, Land & Water
550 West 7th Avenue, Suite 900D
Anchorage, AK 99501-3577
(907) 269-8630
Return to top
|
|