Eagle River Greenbelt Access Pathway Preferred Alternative Map

The project will be constructed in phases as money becomes available:

PREFERRRED ALTERNATIVE

CONSTRUCTION PHASES (using 2009 costs)

PHASE III

Glenn Highway to Briggs Bridge

$6,378,444

PHASE I

Briggs Bridge to North Fork Access

$7,964,101

PHASE II

North Fork Access to Nature Center

$5,011,452

 

TOTAL COST PREFERRED ALTERNATIVE

$19,353,997


Construction Phase Map       Return to Alternative main page


Return to main page