Stake site(s) between May 2 and October 15.
-
Submit application, $100.00 non-refundable filing
fee, and signed Coastal Project Certification Statement to the Shore
Fishery
unit within 30 days of staking site(s) AND between June 1 and October
15.
Get Shore Fishery Lease Application
-
DNR reviews application, then prepares public
notice and faxes it to the newspaper with a copy to the applicant.
-
Applicant pays for newspaper ad.
-
Thirty day public review period begins the first
day the ad is published.
-
Allow approximately 35 days for any protests
to be mailed (the protest date is the date the protest is postmarked).
-
DNR must receive an affidavit of publication,
either directly from the newspaper or from the applicant.
-
If no protests are received, then DNR sends
applicant a shore fishery diagram preparation packet.
-
-
Applicant submits the $150.00 diagram review fee to DNR within
90 days.
-
-
Applicant's draftsperson makes final corrections
and returns it to DNR with original mylar (within 90 days).
-
DNR reviews mylar to make sure all corrections
have been made.
-
DNR prepares lease document and mails to applicant
for signature.
-
Applicant signs 2 original copies of lease document
in front of a notary or postmaster and returns BOTH to DNR with the
$300.00
rental for the first year (no rent payment is required for a lease
amendment if the rent payment is current; lease renewals also require
a $100 renewal fee).